Lukenya Hills Park Housing Development Phase I
Mavoko Municipality, Machakos
Description
Lukenya Hills park housing development phase I comprised of 3 bedroom duplex bungalows each with a plinth area of 96.4 sqm. and a walk around garden. Facilities include front and rear doors, lounge, dining, fitted kitchen, 3 bedrooms (1 ensuite) all with in-built wardrobes. Each house has a 500 litre water tank and landscaped gardens. The project involved site survey, excavation of foundation to put up 56 single storey medium cost housing units for sale. Provision of road network, parking areas, gate, gatehouse and general landscaping. Designing and constructing electrical and mechanical services, and boundary wall and gate construction.

Our services included but not limited to:
- Preparation of Business Plan.
- Preliminary cost estimates of outline sketch proposal.
- Cost plan and cost control of detailed design.
- Prepared bills of quantities and other tender documents.
- List of bidders and tender action.
- Tender evaluation report and tender negotiation.
- Drawing up of contract documents and signing by the parties to the contract.
- Site visits and meetings.
- Re-measurement of works.
- Valuation of work done for preparation of interim payment certificates.
- Ensuring adherence to approved programme of works.
- Prepared and agreed final account with contractor.